*UPDATE July 29th**UPDATE JUNE 29th*Ground packed and gravel set.
Form for the wall is ready.
Cooling fans.
*UPDATE JUNE 26th*Then there was a hole.
*UPDATE JUNE 15th*Floor is cut and ready for pulling.
*UPDATE JUNE 14th*Precision Concrete will be out here around 9am to get the cutting started on the pit. Getting real.
*UPDATE JUNE 12th*Talked with Allison from Dynocom yesterday and I believe the Dyno will be ready on the 16th of July. I anticipate having it here the following week and training/installation will be the weekend of July 26th.
As for this weekend the hole is getting cut into 2' chunks and I will be pulling them out using concrete anchors, then the digging begins. Hope to have concrete in 2 weeks and epoxy the week after.
*UPDATE MAY 31st*Have finally decided to make the jump into the AWD Dyno world. Tried to do this back in 2005, but the funds and location were not there. Now that the automotive community has grown I believe it is time to stop making road trips and have an AWD Dyno closer to home. As of right now my Dyno is made, but I am waiting on the Eddy Brake. Going to be digging a pit and putting it in floor within the next month.
We are just in the beginning stages of this whole project and I believe within a year things will be running full force. There are many other ideas that will be coming later, but the main thing right now is getting the dyno in and running.
I will be taking reservations as there has already been quite the interest. Time will be very limited as I work till 6PM Mon-Fri, but weekends are wide open unless otherwise specified.
Pricing and availability will be posted soon. Stay tuned.